PJM’s Reliability Backstop: Who Pays When Large-Load Growth Outruns Power Supply?
By Paul Turner | Principal, Turner Commodities Law, PLLC
A data center may need 250 megawatts of electricity within two years. A power plant capable of serving that demand may take much longer to build. PJM, the regional grid operator serving much of the Mid-Atlantic and parts of the Midwest, must plan for the possibility that the data center opens on schedule. But what happens if PJM pays to secure additional generating capacity and the data center is delayed, downsized, or never built? Who pays for the capacity PJM arranged to have available? That is the question at the center of PJM’s Reliability Backstop Procurement proposal.
Why This Is a National Issue
For years, utilities planned around modest electricity-demand growth. Now, data centers, artificial-intelligence facilities and industrial projects may seek hundreds of megawatts at a single site, often sooner than new generation and transmission can be developed. A project may benefit its host community, but its requested service date does not establish when sufficient power supplies will be available.
Grid operators must forecast demand and arrange resources before customers begin consuming electricity. Yet service requests are not firm consumption commitments. Projects may be speculative, delayed by financing or permitting, or redesigned as technology changes. Overestimating demand can impose unnecessary costs on existing customers; underestimating it can threaten reliability.
Regulators are responding in different ways. Texas has adopted financial-security requirements for certain large-load interconnections. MISO has proposed a process to study qualifying large loads and related generation together. PJM is addressing a different problem: the cost of obtaining enough generating capacity to meet projected demand. These measures are not interchangeable. They reflect the same underlying concern, however: how to protect the system without making existing customers finance unsupported commitments by new ones. Around the same time it acted on the Reliability Backstop Procurement, FERC also largely rejected PJM’s related proposals for interim large-load service and “bring your own new capacity” interconnection rules, leaving interconnection and curtailment questions primarily with the states.
What PJM Is Trying to Solve
PJM operates a wholesale capacity market. Unlike an energy purchase, which pays for megawatt-hours actually delivered, a capacity arrangement compensates a resource for being available to help meet future system needs. PJM uses forecasts of peak demand, plus a reserve margin, to determine how much capacity the region needs. Its regular auctions procure commitments in advance. When expected demand rises faster than new resources can be developed or cleared through the ordinary process, PJM may forecast a shortage even though the market has not yet produced sufficient additional capacity. The 2028/2029 Base Residual Auction, for example, cleared short by 6,831 MW.
PJM’s proposed Reliability Backstop Procurement, or RBP, is intended to address that potential gap through a one-time supplemental procurement. The justification is straightforward: waiting until a shortage materializes is not a realistic reliability strategy. But buying additional capacity creates a payment obligation. The critical legal and commercial question is how that obligation should be assigned, particularly if the load growth that justified the procurement changes.
Where the Proposal Stands
PJM filed its original RBP proposal with FERC on July 31, 2026, in Docket No. ER26-3380-000. On September 29, FERC accepted much of the proposal, suspended the accepted provisions for five months, until February 28, 2027, subject to refund, and established further proceedings concerning disputed issues in Docket No. EL26-108-000. On October 22, PJM circulated additional proposed terms for stakeholder consultation, with a new filing planned for October 29. Those October 22 terms are proposals, not presently effective tariff obligations.
Under the October 22 materials, PJM proposes to allocate RBP costs by reference to large-load growth between the 2026/2027 and 2028/2029 delivery years. Electric distributors would provide firm customer-level forecasts, with specified customer-level offsets taken into account. Load-serving entities, or LSEs—the companies responsible for serving customers’ electricity requirements—would post collateral equal to 40 percent of their discounted total RBP payment obligations (a reduction from the approximately 50 percent figure in the original filing). Acceptable forms of collateral would include cash, letter of credit, and surety bond. Electric distributors would notify PJM of the relevant large-load information 120 days before a delivery year, and LSEs would post collateral 45 days before that year. The materials also contemplate continuing liability for an LSE that exits (whether or not the exit is caused by a Transmission Owner departure), although the detailed terms and amounts would require a later rate filing. These changes respond directly to the three issues FERC flagged for further procedures: cost allocation, Transmission Owner exit rules, and LSE collateral.
Why Charge the Growing Load?
There is a substantial argument for assigning incremental procurement costs to the load growth that caused the procurement. If PJM buys capacity principally because a new campus is expected to begin operating, spreading the entire cost across unrelated households and businesses may obscure the economic signal and subsidize projects whose demand forecasts are uncertain. Requiring the beneficiaries or cost-causers to bear the incremental cost can encourage more realistic forecasts and investment decisions.
That principle is easier to state than to apply. Generation serves the regional grid rather than a single customer, and an added resource may provide broader reliability benefits. A forecast can be reasonable when made and still prove wrong. A project may offset its demand through onsite generation, storage or enforceable load reduction, but only to the extent the governing rules recognize those measures. A defensible allocation method therefore needs clear forecast standards, meaningful opportunities to correct errors, appropriate recognition of offsets, and safeguards against charging twice for the same capacity service. Otherwise, a cost-causation rule risks becoming a blunt surcharge rather than an accurate assignment of costs.
The Supplier May Bear the Obligation Even After Losing the Customer
Consider a 250 MW data-center campus. Its developer signs a three-year electricity supply agreement with an LSE. The forecasted campus load contributes to PJM’s decision to procure additional capacity. Construction then slips eighteen months. Before the campus opens, the developer changes suppliers. Under the October 22 materials, the transferring LSE would remain financially responsible until the receiving LSE has posted the required collateral and any unpaid invoice amounts associated with the transfer have been settled. The original LSE may therefore have stopped selling electricity to that customer, yet the proposed RBP framework could leave it responsible for a continuing capacity charge and related collateral. Whether that actually occurs will depend on the final tariff, but it is precisely the risk that the proposed exit-liability provisions raise.
The resulting exposure is not simply another electric-bill line item. An LSE may owe PJM after it stops billing the customer. Energy-price hedges may not cover a separate RBP charge, ordinary deposits may be inadequate for multiyear liabilities, and a terminated supply contract may not preserve recovery rights for subsequent assessments.
Collateral Can Be as Important as the Charge
The proposed 40 percent collateral requirement would create an immediate financing burden separate from the ultimate cost of capacity. A letter of credit uses bank capacity; cash collateral ties up working capital; a surety bond carries fees and underwriting requirements. For a competitive supplier operating on thin margins, the cost of posting security may affect the price it can offer, its ability to serve other customers, and its appetite for long-term large-load contracts. The relevant credit exposure is not necessarily the same as ordinary receivables exposure.
Commercial contracts should therefore answer four questions expressly: who supplies and certifies the load forecast; which party ultimately bears any RBP assessment; what security supports that obligation; and what rights survive termination, supplier switching, project cancellation or bankruptcy. If the tariff bills the LSE, the LSE needs a corresponding enforceable recovery right against the customer or another creditworthy party. A general “all applicable charges” clause may not address a later true-up, a surviving obligation or a dispute about whose forecast caused the charge.
Trading, Pricing and Transaction Consequences
The same analysis belongs in trading and structured-supply decisions. Capacity obligations are not the same as energy positions. A trader can hedge expected megawatt-hours and still be exposed to a new capacity charge, a change in the customer’s energization schedule or a collateral call. Fixed-price proposals must state whether RBP is included, excluded or subject to a regulatory-cost adjustment. Portfolio acquisitions should identify existing large-load forecasts, potential RBP allocations and obligations that may survive customer migration. Developers should consider how these costs are allocated among project companies, tenants, onsite-generation providers and lenders.
What to Do Now
PJM participants should identify customers and forecasts that could trigger RBP allocations, model timely, delayed, phased and cancelled projects, and quantify both assessments and collateral costs. They should review supply contracts, guarantees, credit support, assignments and termination provisions to determine whether resulting obligations are allocated and secured. The expected October 29 filing should be tested against those arrangements, particularly its proposed cost-allocation, collateral and exit-liability provisions.
PJM’s RBP proposal illustrates how large-load growth is transforming reliability planning into a question of contractual risk allocation. The critical issue is whether costs attributable to particular forecasts can be assigned fairly and recovered from creditworthy parties. The October 29 filing warrants prompt review, particularly for supply agreements and credit arrangements negotiated before final tariff terms are known.